VIDEO Ce tronsoane din Autostrada Moldovei A7 se mai deschid până la final de an: „Din păcate, lucrările sunt îngreunate de vreme”

Construction on the Bacău – Pașcani section of the A7 highway is ongoing, but not all segments will be completed by year-end. The Transport Minister announced that the stretch from Bacău to Roman will open this year, while the entire route to Pașcani is expected to finish by early 2027. Weather conditions have hindered progress, with current completion rates at 83% for Lot 1, 70% for Lot 2, and 62% for Lot 3. The project has faced delays, with expectations that it should have been completed last year. The total length of the A7 will reach approximately 290 km by year-end, connecting Ploiești to Roman Sud.