Primele aeronave IAR-99 SM au fost livrate de Avioane Craiova cu o întârziere de mai bine de doi ani

Avioane Craiova has delivered the first two IAR-99 SM aircraft after a delay of over two years, with a third expected by the end of November. The modernization program, valued at 275 million lei, aims to upgrade ten aircraft for training Romanian military pilots. Despite previous delays due to supply issues and external factors, the program continues with a new approach from the Ministry of Defense. The contract was signed in August 2020, with an initial four-year timeline, but has faced challenges leading to financial penalties. The remaining seven aircraft are projected for delivery by December 2027.