Primăria Sectorului 3 reduce cu 20 de milioane de lei costul noului parc de pe strada Brățării. Cum explică

The Sector 3 City Hall has reduced the budget for the new park on Brățării Street from 169 million lei to 148.5 million lei. This decrease is mainly due to a reevaluation of private land prices that will be expropriated. The compensation for expropriations has dropped from approximately 90.5 million lei to 70.6 million lei. The reduction is attributed to the removal of three properties from the expropriation corridor and a reassessment of land values based on a market study. The new park will cover about five hectares and include various recreational facilities. The project is expected to take 30 months to complete and will be funded by the local budget.