The A10 Sebeș-Turda highway is undergoing stabilization work due to significant land subsidence at kilometer 66. The contractor is implementing a system of reinforced concrete piles to stabilize the ground, followed by the reconstruction of the road structure. These interventions include deep ground consolidation, drainage system improvements, and the replacement of damaged road signs. The construction company PORR is responsible for the work, which is expected to last about three months, with traffic potentially resuming in early 2027. Currently, traffic is diverted to DN1 due to closures on the affected section.