Construction on the Sibiu-Făgăraș Highway (A13) is progressing, with two sections exceeding 56% completion. The Turkish contractor Makyol employs hundreds of workers and machinery across the 68 kilometers, expected to be finished by 2028. The most advanced section is between Arpașu de Jos and Sâmbăta de Sus, at 56.86% completion, while the second section is at 56.10%. The fourth section is at 48.54%, and the first section has the least progress at 29.46%. The project, funded through the Transport Program 2021-2027, aims to boost economic development in the region by attracting investments and creating jobs. The completion of the highway will enhance connectivity between Transylvania, Muntenia, and Moldova.