Cristian Pistol, the CEO of CNAIR, reports on the progress of the A13 Sibiu-Făgăraș highway construction by Makyol. All four sections are advancing, with varying completion rates. The first section is at 29.46% completion, the second at 56.10%, the third at 56.86%, and the fourth at 48.54%. A total of 1,273 workers and 516 machines are involved across the sections. The project, costing 6.4 billion lei, is funded through the 2021-2027 Transport Program and is expected to be completed by 2028. The highway will enhance connectivity in Romania and create local jobs.