Eurowind Energy România has commenced the delivery and installation of wind turbines for the Frumușița and Pecineaga Nord-Est parks, totaling 138 MW capacity. The first components of Vestas V162 turbines arrived in October, with assembly starting at Frumușița. Deliveries for Pecineaga Nord-Est are also underway, with main components expected by spring 2027 for the third project, Vector. The three parks will feature 23 turbines, with operations expected to begin in 2027. Eurowind has been active in Romania since 2011, managing several solar and wind projects totaling 184 MW, alongside a development portfolio of approximately 7.5 GW.