The final section of Bucharest's A0 ring road faces a design flaw, preventing drivers from Târgoviște from directly accessing the highway. They must reach the DN1A junction instead. The intersection lacks a proper junction, only offering a semi-junction, which complicates traffic flow. Currently, construction is 90% complete, focusing on connecting to national roads DN1A and DN7. The first 10 km may open in 2026, with full completion expected by April 2027.