The first kilometers of the A8 Unirii Highway may be inaugurated in spring 2027, as Turkish contractor Nurol has made significant progress, exceeding 70% completion. The contract for the 24.39 km section between Târgu Mureș and Miercurea Nirajului was signed in February 2024, with construction delays due to phased permit issuance. Despite initial setbacks, the contractor has mobilized effectively, with over half of the road already asphalted and many structures advanced. If the pace continues and weather conditions remain favorable, traffic could open by May 2027.