The construction of the 3C2 Chiribiș – Biharia section of the Transylvania Highway (A3) has reached 90% completion by the end of November, with 200 workers and over 200 machines on site. The National Company for Road Investments (CNIR) showcased images of the 28.5 km stretch in Bihor County. This section, along with the neighboring Suplacu de Barcău – Chiribiș lot, will facilitate highway traffic from Nușfalău to the Borș II border. Current progress includes 98% of stabilized ballast, 95% of the first asphalt layer, and 12% of the final wear layer. The project, valued at 785 million lei, is funded by European funds and the state budget, with a completion deadline of May 20, 2027.