The rehabilitation of the Council Tower in Sibiu is progressing, with 50% completion. The roof will be made of natural copper instead of pre-patinated copper as initially proposed. The project also includes restoring the clock from 1881, which operates mechanically. The works began in January 2026 and are expected to finish by January 2028, executed by Decorint SRL & Domino Construct Expert SRL. Interior and exterior renovations are being carried out using traditional techniques to maintain authenticity, including cleaning and repointing brickwork. The project is funded by European funds through the Central Region Program 2021-2027.