The Margina-Holdea section of the A1 Lugoj-Deva highway is 83% complete, with traffic expected to open in 2027. Construction is being carried out by a consortium of Romanian and Bosnian firms, focusing on tunnel gallery works and hydro-insulation. After completing the galleries, the next steps include road preparation and installing necessary tunnel equipment. All systems will be tested before the opening, and teams will be trained for monitoring and emergency response. This 9.13 km section, including 2.4 km of tunnels, has a contract value of 1.82 billion lei, funded by the state budget, and will enhance highway connectivity between Sibiu and Romania's western border.