economedia.ro/pasajul-de-320-milioane-lei-din-sect

The second phase of traffic restrictions for the underground passage construction at the intersection of Olteniței Road, Vitan-Bârzești Road, and Sergent Ion Iriceanu Street will begin on November 26. The first two lanes and the sidewalk on Vitan-Bârzești Road will be affected, but traffic will continue on two lanes in each direction. Pedestrians can use designated paths, and access to nearby military and fire units will remain open. The project, costing approximately 320 million lei, includes a 442-meter long passage with two lanes in each direction, new sidewalks, a bike lane, and various infrastructure systems. The construction is expected to last two years and is part of a broader infrastructure development program in the capital.