This year, 30 kilometers of the A7 Moldova Highway will be opened, specifically the section from Bacău to Roman. The construction progress is at 83% for lot 1, 70% for lot 2, and 62% for lot 3, with over 1,500 workers and 900 machines on site. The goal is to complete the section by the end of this year, with further extensions planned for next year, depending on weather and funding. The highway remains a national priority, aiming to connect major routes to Constanța, Târgu Jiu, and Craiova by next summer.