The High Court of Cassation and Justice ruled that prices in sectoral procurement contracts must be updated when execution is extended for reasons not attributable to either party, provided legal conditions are met. This decision arose from a dispute between Electromontaj and Transelectrica, where Electromontaj seeks over 37 million lei due to delays in a contract for modernizing a 400 kV power line. The court clarified that the phrase 'may be modified' allows for contract adjustments without re-tendering if legal criteria are satisfied. However, this does not grant discretionary power to the contracting entity or an automatic right for the economic operator to adjust prices. If delays are not the fault of either party, the contracting entity must adjust the contract accordingly.