The High Court of Cassation and Justice clarified that the revocation of urban planning documentation does not prevent the issuance of construction permits if the authorization process was initiated while the documentation was valid. This ruling emphasizes the importance of legal security for investors acting in good faith. The decision arose from a case in Constanța where an investor's urban planning certificate was based on a subsequently revoked PUZ. The court highlighted that the validity of urban planning documents can end through expiration, revocation, or annulment, and stressed that investors should not suffer consequences for legal issues they did not cause. The ruling raises questions about investor protection in cases of judicial annulment of PUZs.