The assembly of the tunnel boring machine for the Poiana tunnel on the Sibiu-Pitești highway is ongoing, utilizing a 400-ton crane. This project marks the first highway tunnel in Romania built with this technology. The TBM's cutter head, weighing 131 tons, arrived in October 2026, and once assembled, it will begin boring the 1,780-meter tunnel. As of October 2026, the physical progress of the Cornetu-Tigveni section reached 18.89%, with work ongoing on various structures and an experimental asphalt section. The construction is led by the Astaldi/WeBuild-Tancrad consortium, with the contract signed in August 2022.