The Regional Directorate of Roads and Bridges Craiova reported progress on the Robești and Balota tunnels of the A1 Sibiu-Pitești highway. Construction by the Turkish company Mapa-Cengiz includes seven tunnels on this section. The Robești tunnel's right gallery is 50% complete, while excavation for the Balota tunnel's left gallery is at 12% and the right gallery at 83%. Work continues based on geological conditions and technical solutions. The project is limited to 45% completion due to pending environmental permits, with expectations for revised permits by December. The highway will enhance connectivity across the Carpathians, supporting the Pan-European Corridor 4.