The National Company for Road Investments (CNIR) and the contractor for the A8 highway section have conducted strength tests on pre-stressed concrete beams intended for bridges and viaducts. Construction began in August 2026, with nearly 20% completion. The tests assess the beams' mechanical performance and compliance with technical specifications. Two beam types, 30 and 40 meters long, were evaluated under maximum loads. The project includes 21 structures requiring 583 beams. Testing involves non-destructive and destructive phases, with a maximum load of 4 x 167 kN applied to a 30-meter beam. The contract for this section spans 34 months, with 10 months for design and 24 for execution.