The European Investment Bank (EIB) has approved a €400 million loan for the modernization of Unit 1 at the Cernavodă nuclear power plant in Romania. This funding is part of a larger €800 million project aimed at extending the unit's operational life by 30 years. The modernization works are set to begin in 2027 and will last three years, ensuring stable energy supply and lower carbon emissions. The total investment for the project is estimated at €3.1 billion, with additional financing sources being negotiated. This initiative supports Romania's energy security and transition to a low-carbon energy system.