The Stremț municipality plans to invest approximately 17.37 million lei in expanding and rehabilitating the sewage system in Stremț and Geoagiu de Sus. The project includes the construction of 6.7 kilometers of new sewage network, connections for 174 households, modernization of pumping stations, and expansion of the existing wastewater treatment plant. The project aims to improve sanitary conditions and reduce soil and water pollution by connecting households to the public sewage system. The implementation is expected to take 24 months, with 18 months dedicated to construction work.