www.g4media.ro/guvernul-actualizeaza-suma-pentru-c

The Romanian government has reapproved the technical-economic indicators for the construction of a stadium in Târgoviște, with an updated total cost of 425 million lei. The investment, managed by the National Investment Company, is currently 65% complete. The cost increase is due to necessary technical modifications, updated contractual prices, and changes in VAT rates. The project includes significant infrastructure adjustments for safety and functionality. Funding will come from the Ministry of Development and the Dâmbovița County Council, with remaining work valued at 234.14 million lei and an estimated completion time of 13 months.