The Alba County Council plans to build a new bridge over Valea Gârbova on DJ 106F, replacing the existing one. The project is estimated at 7.26 million lei and will take six months to complete. A temporary detour will be established for traffic during construction. The new bridge will be 35.23 meters long, with a single span of 26.3 meters and a roadway width of 7.8 meters. It will include sidewalks and protective barriers. The project also involves modernizing access ramps and ensuring proper drainage to prevent flooding. Environmental approval has been requested from the Alba County Environmental Directorate.