www.wowbiz.ro/reactoarele-nucleare-de-la-cernavoda

Both reactors at the Cernavodă Nuclear Power Plant were shut down due to a non-nuclear malfunction, impacting Romania's energy system. This incident occurred shortly after Unit 1 was resynchronized to the national grid. As a result, energy imports increased significantly, with Romania importing nearly 1.5 times more electricity than the previous day. Nuclearelectrica confirmed that the shutdown was in accordance with operational procedures and posed no nuclear safety risks. The company is prioritizing repairs and plans to replace the Technical Director by December 1, 2026, to ensure equipment availability for Unit 1's operation.