Railway infrastructure modernization works on the Bucharest Progresu – Jilava – Giurgiu Nord – Giurgiu Nord Frontier continue despite adverse weather conditions. The physical progress of the contract has reached 22%. Ongoing activities include dismantling existing infrastructure, platform preparation, and construction of new passenger buildings. Electrification efforts are underway, with 80% completion on certain sections. The project, valued at 2.108 billion lei, aims to enhance speed, capacity, and safety of rail connections between Romania and Bulgaria, with completion expected by September 2028.