As of early November, 4,692 linear meters of geotechnical drilling have been completed for the A3 Ploiești – Brașov Highway feasibility study, representing 13.97% of the approved total. The contractor requested about 132,000 meters, but only 33,500 meters were approved for the feasibility phase. The study is expected to be completed by December 31, 2028, with the contract extended by 493 days due to documentation revisions. The final contract deadline is June 19, 2031. Payments have not been made by CNIR since taking over the contract, although previous payments were made under CNAIR. The feasibility study contract was signed on February 15, 2021, for 46.55 million lei, with Consitrans as the winning bidder. This project is a priority for the TEN-T transport network.