The Brăila-Galați express road, measuring 10.76 kilometers, is 98% complete, with final touches being made by the Romanian contractor UMB. Key work is focused on the cable-stayed bridge, where 64 of the 96 cables and 32 of the 204 slabs have been installed. Upcoming tasks include completing the remaining slabs, applying waterproofing, installing barriers, and laying asphalt. The project, valued at 449.4 million lei, is funded by European Union resources. The Transport Minister emphasized that all technical conditions must be met for safe traffic opening. Additionally, around 200 kilometers of highways and express roads are expected to open this year, with 71 kilometers already completed.