economedia.ro/ambele-reactoare-de-la-cernavoda-au-

Both reactors at the Cernavodă Nuclear Power Plant were unexpectedly shut down, leading to zero nuclear energy production in Romania. Unit 1 was halted due to a defect in the turbine's vacuum control system, while Unit 2 was affected by low water levels in the Danube. Nuclearelectrica assured that nuclear safety remains unaffected. The reactors are expected to restart gradually, with Unit 1 having been restarted over the weekend and Unit 2 anticipated to resume operations on Tuesday. The shutdowns have previously caused significant financial losses, and the country will rely more on hydro, wind energy, and imports during this period.