www.antena3.ro/actualitate/a-repornit-si-reactorul
The Ministry of Energy announced that Unit 2 of the Cernavodă Nuclear Power Plant is expected to be operational on November 10, 2026, following the initiation of the reactor startup sequence on November 9. Prime Minister Luca Niculescu visited the plant alongside the Energy Minister after Unit 1 was reconnected to the national grid. As of Monday morning, total energy production was 5863 MW, with the highest share coming from hydrocarbons and hydro sources. Both units were previously shut down due to low water levels in the Danube during summer.