The Cernavodă Nuclear Power Plant's Unit 1 has resumed operations after nearly 100 days of downtime due to low Danube water levels. Prime Minister Luca Niculescu announced that the reactor is currently operating at 50% capacity and will reach full capacity within 24 hours. This unit contributes about 8% of Romania's energy production, alleviating pressure on the national energy system and reducing imports during peak hours. A technical analysis for Unit 2's restart is scheduled for Monday. Niculescu emphasized the need for urgent projects to ensure water supply for cooling and highlighted the importance of nuclear energy in Romania's energy mix, estimating losses from the shutdown at around 1 billion lei.