The investment in Brașov's new Multipurpose Hall is increasing as construction progresses, with a new contract amendment signed by the National Investment Company. The contract value rises by over 26 million lei, totaling approximately 324 million lei. Originally awarded in 2022 for about 276 million lei, the contract has seen increases due to rising material costs and additional work. Construction began in September 2022, with the completion date extended to June 2027 due to technical and weather challenges. The venue will feature a main arena with over 11,000 seats for sports and up to 15,000 for concerts, and will host various cultural events.