www.economica.net/victorie-pentru-ministerul-energ
The High Court of Cassation and Justice rejected appeals from Bankwatch Romania and Transgaz regarding the Tuzla-Podișor gas pipeline construction authorization. This decision is crucial for a strategic project valued over 500 million euros, which will transport gas from Neptun Deep to the National Transport System. The pipeline is already operational, with production expected to start in 2027. Delays could impact Romania's energy security and consumer costs. The court upheld a previous ruling that deemed Bankwatch's claims as time-barred, emphasizing that such legal actions can lead to increased costs and resource consumption, ultimately affecting Romanian consumers.