Construction of the Buftea Beltway, led by Porr, has surpassed 65% completion, according to Cristian Pistol from CNAIR. The Austrian contractor is currently focused on earthworks, reinforcements, passages, and utility networks. A section is expected to be completed by December to facilitate traffic from A0 to DN1A. Progress has been steady in the Bucharest-Ilfov area, promising economic opportunities. In March, the physical progress was reported at 17.9%. The contract for the project was signed in October 2024, with a budget of 281.17 million lei and a timeline of 34 months for completion. The 5.77 km bypass is funded through the Transport Program and will connect to DN1A.