bizbrasov.ro/2026/11/04/centrala-solara-brasov-stu
The photovoltaic park in Stupini faces ongoing challenges for local authorities, despite its previous inauguration. The new administration has identified several issues needing resolution before the project can operate. Key tasks include road access, connection to the National Energy System, and communication infrastructure. A contract worth 37,940 lei has been awarded to Digi România for a fiber optic network to facilitate real-time data transmission from the solar plant to the municipality. The project, funded by the EU, aims for a 20 MW capacity but has faced delays, with a new operational target set for December 2026. The facility consists of 30,380 solar panels and 57 inverters.