The deadline for the feasibility study of the A13 Bacău–Brașov highway has been extended to March 9, 2028, due to delays. The project is currently 52.35% complete, with topographic surveys and demining finished. Geotechnical investigations are at 74.32%, while laboratory tests are at 38.60%. The initial contract was signed on July 22, 2024, with a value of 81.2 million lei, and was originally set for completion in January 2027.