bizbrasov.ro/2026/11/02/prelungiri-proiect-autostr
The feasibility study for the Brașov – Bacău Highway has been extended to March 2028, with overall contract completion now set for April 2036. The study is over 52% complete, with geotechnical investigations at 74.32%. The contract was signed on July 22, 2024, with a value of 81.2 million lei. Laboratory tests are 38.60% complete, and design activities are ongoing. Archaeological investigations are in progress, while demining activities are fully completed. The initial contract duration was 125 months, including 60 months for geotechnical monitoring and technical assistance.