VIDEO | Tronsonul Suplacu de Barcău - Chiribiș se deschide de 1 decembrie
The A3 highway section between Suplacu de Barcău and Chiribiș will open on December 1, with over 90% of the work completed. The final asphalt layer is laid on 20 kilometers, and the contractor is focusing on finishing touches near Suplacu de Barcău. This section has a complicated history, having been initiated by Bechtel and facing multiple contract cancellations. The Chiribiș-Biharia segment, part of the Transylvania Highway, is crucial for connecting the border with the completed Suplacu de Barcău-Chiribiș section. Currently, 5.35 kilometers of A3 are operational in Bihor, linking to Hungary's M4 highway.