VIDEO | Șantier pe lotul 1D Joseni-Ditrău al Autostrăzii A8: peste 300 de muncitori și 240 de utilaje în șantier
Construction on the 1D Joseni-Ditrău section of the A8 highway is progressing rapidly, with over 300 workers and 240 machines currently on site. The project involves earthworks, ground improvements, and the construction of various structures, including bridges and wildlife crossings. The section spans 14.4 kilometers and will feature 18 bridges, passages, and viaducts, along with a road junction and a temporary connection to the next section.