VIDEO | O mie de muncitori lucrează la Autostrada Moldovei A7, pe unde vom merge de la București la Bacău. Care este stadiul lucrărilor • Infrastructură București
Cristian Pistol, director of CNAIR, announced that 1,000 workers are mobilized on the Răcăciuni-Bacău section of the A7 highway, with significant progress reported. Key structures are nearing completion, including two railway overpasses and a junction. The overall physical progress of the project is at 84%, with an investment of 1.673 billion lei funded by PNRR. Traffic will be temporarily closed at Bacău Sud for final connections, with detour details to be provided later.