VIDEO | Nuca tare de pe Autostrada Bucureștiului e încă greu de spart. Chinezii care fac L3 al A0, Lotul Leneș, se luptă cu pasajul crucial de la DN3. Oficial MT: Facem presiuni • Infrastructură București
Irinel Ionel Scrioșteanu, Secretary of State in the Ministry of Transport, visited the Lot 3 construction site of the A0 Highway, emphasizing the need for increased mobilization from the contractor to complete the project by the end of October. The focus is on the DN3-A0 overpass, crucial for connecting Brănești and Pantelimon. Current progress exceeds 96%, with ongoing work on access ramps and the crown beam. Once the waterproofing is completed, the project will enter its final phase, allowing for the opening of this highway segment, which is vital for traffic continuity between major routes.