VIDEO Lucrările la autostrada dintre Sibiu și Făgăraș au depășit 50% pe unul dintre loturi. Șoseaua trebuie finalizată în întregime în 2028 • Administrație Biz Brasov

Construction on Lot 2 of the A13 Sibiu – Făgăraș highway has surpassed 50% completion, according to Makyol's representative. The Turkish company is responsible for the entire 68 km stretch. Despite challenges, the team has shown determination and engineering excellence. Work on the highway's four sections varies between 17.77% and 44% completion, with a deadline set for 2028. The total contract value for the project is 6.4 billion lei, funded through the Transport Program, highlighting its significance for regional connectivity.