VIDEO | Drum complet, în premieră cu mașina, pe L3 al A0 Nord - Lotul Leneș din Autostrada Bucureștiului. Oficial MT: Chinezii încă mai au de lucrat la mobilizare • Infrastructură București
Images from Lot 3 of the A0 North Highway in Bucharest show progress as the construction mobilization improves. Secretary of State Irinel Ionel Scrioșteanu emphasizes the need for increased efforts to complete the lot by the end of October. Key tasks include road markings, installation of sound barriers, and ongoing work on various passages. The completion of this section is crucial for connecting with Lot 4, which is already finished. Scrioșteanu plans to frequently visit the site to ensure timely progress and minimize traffic disruptions during the construction of the interchange with DN3.