VIDEO Calea ferată Brașov - Sighișoara. Noile gări de pe traseu încep să prindă contur - Economica.net
CFR Infrastructură has shared updates on the construction of subsections 1 and 3 of the Brașov - Sighișoara railway line, with completion expected by summer 2028. The latest monitoring report indicates a physical progress of 58.40% on the project, which spans 84 kilometers. Specific details on tunnel construction reveal varying completion rates, with some tunnels fully excavated while others are not yet under construction. The project is managed by a consortium led by Alstom Transport S.A. and involves multiple partners.