VIDEO | Autostrada Moldovei A7 Bacău - Pașcani. Pe lotul 1 Săucești – Trifești, stadiul fizic al lucrărilor a depășit 62%, a anunțat DRDP Iași

DRDP Iași has released new images from the A7 Bacău – Pașcani highway construction site, showing over 62% completion on the Săucești – Trifești section. The main challenges include constructing bridges and road junctions, while work continues on safety features. The project is funded by European funds, with completion expected by August 2026. Recent negotiations with the European Commission have secured funding for all six sections of the highway, emphasizing the importance of meeting deadlines to access nearly 2 billion euros in non-reimbursable funds. The progress on the project is reportedly ahead of official reports.