VIDEO Autostrada Bucureștiului A0: Care mai este stadiul lucrărilor în cel mai fierbinte punct de pe lotul chinezilor, așteptat în trafic la toamnă - Economica.net
The completion of Lot 3 Nord of the A0 Bucharest Highway is projected for October, according to Transport Secretary Irinel Ionel Scrioșteanu. The critical point of the project is the DN3 overpass, which is essential for connecting Brănești and Pantelimon. Current progress includes the installation of the metal deck and ongoing work on ramps and road markings. The project is 91.5% complete, with a total length of 8.6 km and a contract value of approximately 398 million lei, funded by non-reimbursable European funds.