VIDEO | Autostrada A1 secțiunea Margina - Holdea, stadiu fizic de 72%
Asphalt is being laid on the first kilometers of the A1 Margina – Holdea highway section, with overall construction progress at 72%. The project, valued at 1.82 billion lei, is funded by PNRR. UMB Spedition is currently laying the base layer over 4 km and has used about 3,000 tons of asphalt. Additionally, the prefabricated beam factory has been set up, with 18 beams already delivered. Tunnel works are ongoing, with significant progress in both tunnels. Once completed, this section will connect Boița to the western border of Romania, covering over 360 km of highway.