VIDEO | A1 Sibiu-Pitești, secțiunea Cornetu-Tigveni, stadiu fizic de 17,35%
The A1 Sibiu-Pitești Section 3 Cornetu-Tigveni is currently 17.35% complete, with ongoing construction activities by a consortium of Italian and Romanian companies. The project involves significant earthworks and structural developments, pending environmental approval for further progress. Key structures include a tunnel and numerous bridges, with work on 14 structures already underway. The contract value is 5.323 billion lei, and the section is part of a larger European corridor project. Completion is expected by 2028, with potential earlier openings for some sections.