„Vicii ascunse” pe Autostrada A7. CNAIR cere penalități de 43 de milioane de lei pentru deficiențe grave pe lotul Mizil-Pietroasele
The construction of the 28.35 km Lot 2 Mizil–Pietroasele of the A7 highway faced significant delays and issues, leading to penalties of 43 million lei. Problems included non-compliance in metal structures, asphalt layers, and hidden defects. The contractor was required to monitor certain structures and rectify various deficiencies, including inadequate asphalt thickness and poor adhesion between layers. The project, initially contracted for 1.25 billion lei, was delayed by 43 days, with the final inspection occurring on October 17, 2025. The contractor's approach was criticized for prolonging the work and creating new issues, resulting in the imposition of penalties for the delays.