Un nou tronson din Autostrada Transilvania ar putea fi deschis în decembrie, cu un an mai devreme
The Chiribiș-Biharia section of the A3 highway may open in December 2026, ahead of schedule, depending on weather conditions. Construction is over 60% complete, with rapid asphalt laying. The contractor aims for quality work despite challenges in material supply. Daily progress includes laying 3,500 to 4,000 tons of asphalt, with about 700 workers on site. The project, spanning 28.55 km, is crucial for connecting to Hungary's M4 highway. Authorities are optimistic about meeting the new deadline, but adverse weather could delay progress.