Spitalul Regional Iași: La cât au ajuns lucrările?
Construction at the Regional Emergency Hospital in Iași is progressing, with external excavations completed and main building excavations at 89%. Foundation and infrastructure work continues, including reinforcement and stability checks. The contract for construction was signed in October 2025, awarded to a Turkish consortium for nearly 1.7 billion lei. The project includes multiple buildings with advanced facilities and is funded through the Health Program 2021-2027, with EU contributions of 362.94 million lei.